Construction Updates on the Buffalo Main Street Project by WYDOT Revealed
The Buffalo Main Street Project in Wyoming is nearing its completion, with most of the work in the downtown area almost finished, allowing for relatively smooth traffic flow, according to the Wyoming Department of Transportation (WYDOT) [5].
The project, which began some time ago, has seen significant progress. The culvert project connecting Main Street to the Interstate bypass has been completed [2], and traffic on South Main Street at the Cemetery Creek Culvert has been moved to the west side of the culvert project as of June 28 [6].
As of July 23, WYDOT reported progress on various components, with centerline tabs (markings) scheduled to be completed by the end of July [2]. Updates from mid and late July indicate that construction continues, but major work phases are wrapping up [1][3]. However, there was a note of a problem affecting work given to the City Council on July 21, though detailed impacts on the schedule were not specified [4].
For questions or concerns about the project, contact Laura Dalles, Senior Public Relations Specialist with WYDOT District 4 in Sheridan. While the search results do not explicitly provide direct contact information for Laura Dalles, she is referenced as a contact person in the typical WYDOT District 4 communication chain. For detailed inquiries, contacting WYDOT District 4’s main office would be advisable to reach her or get her direct contact details [7].
In addition to the Main Street work, utility work on North Main Street from Fort to Hart Street is nearing completion.
The project also includes work on the Clear Creek Bridge, with contractors set to place an epoxy overlay on the bridge from July 28 through July 30, weather permitting [3]. During this time, traffic on the west side of the bridge will be affected, and West Fetterman and the parking area in front of the Busy Bee and Occidental will be closed [8]. Pedestrians are advised to use sidewalks with caution during the construction period [9].
WYDOT reminds the public that sidewalks are closed to bicycles and electric bikes.
In summary, the Buffalo Main Street project is near completion in the downtown section with manageable traffic impacts. Final touches like centerline marking are ongoing as of late July 2025. For direct communication with Laura Dalles or specific scheduling questions, contacting WYDOT District 4 directly is recommended since exact contact info was not found in the available sources [1][2][3][4][5].
The project, involving industry, finance, and transportation, has seen progress in various components, such as the completion of the culvert project connecting Main Street to the Interstate bypass and the ongoing work on the Clear Creek Bridge, which includes an epoxy overlay that may affect traffic and pedestrian movement. For questions or concerns, contacting Laura Dalles, Senior Public Relations Specialist with WYDOT District 4, is recommended to get the latest updates and detailed information on the project's schedule.